De-Installation & Detour Map

On Sunday, October 25th from 2am to approximately 5pm, certain streets and lanes will be closed in order to de-install the Greenway Echelman Sculpture.  Closures and detours were determined by the City of Boston Transportation, Police, and Fire Departments along with MassDOT and other agencies.

De-installation and Detour Information:

Sunday October 25, 2015 2AM - 5PM

Affecting Purchase St, Atlantic Ave., Pearl St., Oliver St. & I-93S Exit 23

De-Installation Timeline:

2:30-3:30AM  - Traffic management implementation, street closures begin.

Early Morning - Sculpture supported with cranes, begin de-tensioning.

8:00AM-NOON - Public Information Tents Open; One on Congress Street (Between Purchase Street and Atlantic Avenue) and One on Oliver Street (Between Purchase Street and Atlantic Avenue)

Late Morning - Crane lifts sculpture to highest point then lowers into designated container.

Afternoon - Equipment removed from site, streets re-open as public safety allows

 

See below for a map of what to expect during the de-installation process.